04/28 2013
PROJECT OVERVIEW:- Project Name: Temporary District Cooling Plant-2 (TDCP-2) - Saadiyat Dalkia Client: Dalkia Utilities/ TDIC Contractor: Aggreko Middle East Sub-Contractor: Al Naser Electrical Const. Est. Duration: 4-Months AL NASER considered TDCP-2 as a very challenging project since it is a fast paced project and the materials/equipment requires long lead times. It includes civil works and buildings, supply and installation of all electromechanical works, testing and commissioning, energization and handing-over of the 5 Transformers and 22kV S/S’s including the HV Panel. Al Naser succeeded and handed over the project on-time and received an appreciation from the Client and the Contractor | ||